Pre-Construction:  

In order for a project to proceed to construction, the Developer/Owner/Engineer/Contractor shall have a stamped approved site plan from Spotsylvania County’s Planning Department

When site plan approval has been issued, material submittals in accordance with DSM-Final-Article-4-Approved-Materials-and-Manufacturers-List shall be submitted on the Project Tracking Portal to the appropriate project.  

After the material submittals have been approved, the Developer/Owner/Engineer/Contractor will be eligible to schedule a Pre-Construction Meeting with the Utilities Development Services team. If you would like to schedule a Pre-Construction Meeting, please visit the Project Tracking Portal.  

Once the Pre-Construction Meeting is complete, the Utilities Development Services Manager will assign a Construction Inspector to the project and Construction Authorization will be granted.